Since the granting of the Planning Permit in 2011, considerable work has been done to put in place the many different arrangements necessary to construct and operate a wind farm. These include:
The expected timeline for the construction of the wind farm is shown below.
| '07 | '08 | '09 | '10 | '11 | '12 | '13 | 2014 |
|
||
| Identification of site | . | Jan 07 | ||||||||
| Preliminary feasibility studies | ........ | ....... | ....... | 2007 - 2009 | ||||||
| Community consultation | ....... | ....... | ....... | Jan 2010 onward | ||||||
| Lodgement of Planning Application | . | Feb 2010 | ||||||||
| Receipt of planning approval | ... | May 2011 | ||||||||
| Contract negotiation & turbine order | .. . | 1st half 2013 | ||||||||
| Wind park design | .... | 2nd half 2013 | ||||||||
| Construction and commissioning | ... | .. . | late 2013->2014 | |||||||
| Operation | .... | mid 2014 onward |