Timeline

Since the granting of the Planning Permit in 2011, considerable work has been done to put in place the many different arrangements necessary to construct and operate a wind farm. These include:

  • Discussions with potential investors and providers of debt funding
  • Conducting a tender process for the selection of turbine supplier and balance of plant contractor
  • Organising detailed grid connection studies in concert with Network Service Provider Powercor
  • Sourcing a Power Purchase Agreement for the sale of energy and Large Scale Generation Certificates (LGCs)
  • Finalising arrangements with the landowner
  • Detailed planning in regard to compliance with the Permit Conditions
  • Corporate structuring to provide investment opportunities for the community

The expected timeline for the construction of the wind farm is shown below.

'07 '08 '09 '10 '11 '12 '13 2014  

Identification of site .     Jan 07
Preliminary feasibility studies ........ ....... .......     2007 - 2009
Community consultation ....... ....... .......     Jan 2010 onward
Lodgement of Planning Application .     Feb 2010
Receipt of planning approval ...     May 2011
Contract negotiation & turbine order .. .     1st half 2013
Wind park design ....     2nd half 2013
Construction and commissioning ... .. .   late 2013->2014
Operation ....   mid 2014 onward